Intel causa sensación en New Albany.

octubre 23, 2026, 9:51 pm | Intel

Construction Enters a New Phase

Intel’s Ohio megaproject has reached another visible milestone. Crews have lifted the first major structural steel truss into place at the company’s first semiconductor fab in New Albany, kicking off a new stage of construction at one of the largest building projects in Ohio.

Steel Rises Over the First Ohio Fab

Intel announced on Oct. 21 that the first truss was installed at the first of two fabs planned for the initial phase of its Ohio campus. Drone footage released by the company shows the steel frame climbing above a large concrete foundation. The announcement was Intel’s first update on the Ohio project since winter.

Naga Chandrasekaran, Intel Executive Vice President and Chief Technology and Operations Officer for Foundry Manufacturing, marked the moment in a post on the company’s website. 

“This represents another significant step toward expanded U.S. leading-edge semiconductor capacity and a visible reminder that the future of American manufacturing is being built today,” he wrote.

A Signal of Intel’s Commitment to Ohio

Dorsey Hager, Executive Secretary-Treasurer of the Columbus/Central Ohio Building and Construction Trades Council (C/COBCTC), said the milestone sends a clear message.

“It’s a huge milestone and shows the community, the state and the nation that Intel is committed to this project,” Hager said.

Building Trades Workforce Expected to Nearly Triple by 2028

As the building’s framework goes up, Hager anticipates the number of tradesmen and tradeswomen needed on site will grow as well. Manpower has held steady so far in 2026. 

“There are 1,600 currently on site,” he said, adding that over the next two years, he expects that number to climb sharply.

“We’ll need about 2,500 construction workers in 2027, and it will ramp up to about 4,500 in 2028,” Hager said.

Progress at the Ohio Site

According to Intel’s required annual report to the Ohio Department of Development, the company spent $1.5 billion in 2025. That work covered an office building and infrastructure, including a boiler/chiller plant and a water purification plant. By year’s end, cumulative spending and contractual commitments at the site reached $7 billion of the project’s $28 billion total.

Construction started in 2022, about six months after Intel announced the site, and went vertical two years ago. The trusses now indicate the project is approaching a new phase.

Overcoming Years of Delays

The milestone arrives as the megaproject, which has been delayed several times, begins to show real progress.

Early setbacks included Congress’s slow passage of the CHIPS Act and financial troubles that drove Intel’s stock down to $18.13 in early April 2025, a 16-year low.

In 2025, Lip-Bu Tan succeeded Pat Gelsinger as CEO and signed major investment agreements with the federal government, Nvidia and SoftBank. Under the company’s deal with the Trump Administration, the U.S. now holds a 10 percent stake in Intel.

Intel’s financial challenges directly affected the project schedule, which was reset last year. The company now expects to open Ohio One in 2030 and Ohio Two in 2031, years later than the original 2025 target that Intel once described as “aggressive.”

What Comes Next: Equipment, Customers and Jobs

Intel has said that outfitting and opening the fabs will cost more than constructing the buildings, and completing that phase hinges on securing customers for the plant’s most advanced chip designs.

In September, reports emerged that memory chip maker SK Hynix might lease foundry space in Ohio to produce memory chips, though neither company has confirmed any plans.

“Demand for computing power is growing at an unprecedented pace,” Chandrasekaran wrote. “Meeting this demand requires some of the most advanced research and development, engineering and manufacturing work ever undertaken.”

Once open, the two fabs are expected to create 3,000 jobs, Columbus Business First reported.