Public works projects led by union signatory general contractors finish sooner and encounter far smaller cost overruns than those led by non-union contractors, according to a new study of 128 projects.
The results back up what Ohio building trades leaders have argued for years in support of Project Labor Agreements (PLAs) and union construction labor: the work gets done on schedule and on budget.
About the “Union Contractors Deliver” Report
NorCal Construction Industry Compliance (NCIC), a joint labor-management organization, released the report, titled “Union Contractors Deliver,” in July. Its authors are Matthew Hinkel, an economist at Alma College in Alma, Mich., and Larissa Petrucci, an NCIC policy and research analyst with a doctorate in sociology.
The researchers reviewed 128 public works projects in Sacramento County, Calif., all finished between 2018 and 2022, with an average cost of roughly $6.5 million. They used statistical models that controlled for project type, start year and infrastructure category to compare results of projects with union signatory prime contractors against those with non-union primes.
Non-Union Projects Ran Far Over Budget
On average, final costs across all projects in the study came in at $235,866, or about 3 percent, above the original contract amount.
The difference between union and non-union work was dramatic. Non-union projects finished an average of $511,123 over their starting costs. Union projects averaged just $41,351, or 1.9 percent, a more-than-tenfold gap.
When other pricing factors were taken into account, cost increases on projects with a union signatory prime contractor were 4.9 to 6.3 percent less.
Union Contractors Finished Weeks Sooner
The average project in the study took 274 calendar days, or roughly 39 weeks, to complete. Union contractors finished an average of 15 days ahead of non-union contractors. After controlling for other factors, building trades contractors completed projects 14 percent to 22 percent faster, finishing 38 to 60 days earlier than their non-union competitors.
Training and Productivity Drive the Union Advantage
The authors credited the union edge mainly to worker productivity and training. They cited prior research, including a study of 1,550 union and non-union projects, showing that union labor is linked to about a 4 percent reduction in project costs.
Other research found union jobsites were at least 30 percent more productive on office building projects and as much as 20 percent more productive on school projects. As a result, the authors wrote, higher union wages may not lead to higher total construction costs.
The study suggests Registered Apprenticeship Programs account for much of that advantage. Union construction workers who finish a Registered Apprenticeship Program can earn as much as 33 percent more than those who do not. The authors also found that over the last decade, union apprentice wages have kept up with inflation, while real wages in management-controlled programs dropped by 12 percent.
Training at Joint Apprenticeship Training Committees helps apprentices and journeymen work more safely and more efficiently. Together with union contractors’ stronger access to manpower, these factors help union-built projects reach completion sooner.
The report also referenced research showing union construction jobsites generally have fewer health and safety violations than non-union projects.
Support for Project Labor Agreements
The study comes as building trades leaders nationwide promote PLAs and Community Benefit Agreements as tools to control costs, keep projects on schedule and guarantee access to a trained workforce.
The findings strengthen that case. The authors pointed to a separate peer-reviewed study of Sacramento County that found PLA projects were completed 15 percent to 17 percent faster on average than non-PLA projects, likely because of the highly skilled, highly trained union workforce used on PLA and CBA projects.
The report concluded that collectively bargained labor standards do not sacrifice cost-effectiveness or timeliness. According to the authors, delivering projects faster and on budget benefits contractors and workers, as well as the taxpayers who fund public works and expect a return on their investment.